Ashdod-Ashkelon offshore pipeline project — onshore worksite during execution
ASHDOD PULL-IN OFFSHORE ASHKELON
A&S Global / Experience / Ashdod – Ashkelon
Selected Project Experience

Ashdod – Ashkelon.

A 36" offshore high-pressure gas pipeline forming a new southern offshore transmission loop, with HDD landfalls at two coastal sites. Multi-phase involvement from execution under Maagan through to pre-commissioning under A&S Global.

Project location
Ashdod & Ashkelon
Two-landfall offshore loop
Pipeline length
42km
Pipeline size
36"
Landfalls
2
Ashdod & Ashkelon
Method
HDD landfalls
+ onshore pull-in
Network
Southern offshore
transmission loop
01

Project overview

A 36" offshore pipeline forming Israel's new southern transmission loop.

The Ashdod–Ashkelon project consists of approximately 42 km of 36" offshore high-pressure gas pipeline, with HDD landfalls at two coastal sites — forming part of Israel's offshore natural gas transmission infrastructure expansion as a new southern transmission loop.

The project combined offshore pipeline installation, trenchless landfall crossings at both sites, onshore pull-in operations, marine and onshore interface coordination, and pipeline pre-commissioning — executed by a multi-national contractor team operating across two parallel landfall sites within Israel's regulatory and operational environment.

Two parallel landfall sites operating simultaneously create execution density rarely seen on single-landfall projects: weather windows, marine spread availability, and interface coordination must be synchronized between Ashdod and Ashkelon.

Ashdod onshore pipeline worksite — pipe staging and installation

Onshore worksite — pipe staging and welding operations

02

Role of A&S Global

Sustained involvement across the full project lifecycle.

Project Continuity

Project involvement began through Maagan Marine & Diving Works, where A&S Global's founder served as Project Manager across the primary execution phases — site establishment, HDD landfall operations at both sites, onshore pipeline welding, onshore pull-in, and the subsequent offshore support and tie-in activities.

Following the main construction phase, involvement continued independently through A&S Global during the project's pre-commissioning stage — providing operational continuity built on existing site knowledge, established contractor interfaces, and familiarity with both offshore and onshore execution environments.

Function
Project Manager — main execution + pre-commissioning
Engaged through
Maagan (execution) · A&S Global (pre-commissioning)
Phases involved
Site setup → HDD → welding → pull-in → tie-in → pre-commissioning
Sites
Two parallel landfalls — Ashdod and Ashkelon
03

Execution phases

Five phases — one continuous involvement.

Phase 01

Site Establishment & Worksite Operations

Setup and ongoing coordination of two parallel onshore worksites at Ashdod and Ashkelon — operational base for the offshore installation campaign and associated subcontractors at both sites.

Site coordination, local execution support, logistics interfaces, contractor support, and worksite readiness across both landfall locations throughout the campaign.

Phase 02

HDD Landfalls — Two Sites

Trenchless landfall crossings at both Ashdod and Ashkelon. Local site coordination, contractor support, and interface management between the offshore pipeline works, the landfall areas, and the parallel onshore worksites.

Direct Pipe / HDD operations at two parallel sites
HDD trenchless landfall operation — pipeline pulling spread
Phase 03

Onshore Pipeline Welding

Onshore pipeline welding spreads at both sites. Site-level coordination and interface support between welding contractors, local support teams, and broader project operations — bridging HDD exits, onshore facilities, and tie-in readiness for later commissioning.

Phase 04

Onshore Pull-In & Tie-In

Pipeline pull-in operations and subsequent offshore support and tie-in activities, integrated between the marine spread and the onshore worksites at each landfall.

Two parallel pull-in operations create execution density rare in single-landfall projects — weather windows, tension management, alignment tolerances, and contractor synchronization must converge across both sites.

Phase 05

Pre-Commissioning — under A&S Global

Pipeline pre-commissioning operations including flooding, cleaning, gauging, hydrotesting, dewatering, drying and nitrogen packing — coordinated between the two landfall sites with pig launchers and receivers, water handling systems, and temporary pre-commissioning equipment.

This is the phase where engagement transitioned from Maagan to A&S Global directly, providing operational continuity built on the prior phases.

04

Project participants

Multi-national contractor team operating across offshore and onshore scopes.

Israel Natural Gas Lines
Client
Project owner and operator of Israel's high-pressure gas transmission system.
Micoperi S.r.l.
Main Contractor
Offshore EPC and marine integrator awarded the offshore pipeline package.
Maagan Marine & Diving Works
Local Support Contractor
Israeli operational backbone — civil works, landfall support, and onshore execution across both sites under subcontract to Micoperi.
A&S Global
Pre-Commissioning
Onsite project management for pre-commissioning operations across both landfalls.
+ Specialist subcontractors
Across phases
HDD, welding, marine spread, and pre-commissioning specialists engaged across the project's execution phases.
05

Value delivered

Continuity, contractor familiarity, and practical site knowledge.

In multi-contractor offshore projects, the most common failure mode is interface breakdown between phases — “nobody remembers why this was done,” “that was another contractor,” “design doesn't match field reality.” Continuity across the execution chain is what closes those gaps.

i.

Execution Continuity

Single point of project knowledge spanning early site works through pre-commissioning — a perspective rarely held by any other party on the project.

ii.

Contractor Coordination

Established working relationships across all major project participants — international main contractor, specialist subcontractors, and the local support contractor.

iii.

Site Knowledge

Practical understanding of buried infrastructure realities, as-built conditions, unresolved field issues, and how the worksite evolved across phases.

iv.

Interface Management

Practical bridging between international project execution standards and the local operational realities of working in Israel — Hebrew-language interfaces, local authorities, and supply chain depth.

In closing

Practical project management. Local coordination. Hands-on execution.

The Ashdod–Ashkelon project reflects sustained involvement across multiple phases of a major offshore pipeline programme — from civil execution under Maagan to direct pre-commissioning engagement through A&S Global. Continuity, contractor familiarity, and practical site knowledge carried across both landfalls.

Project participation acknowledged with prior consent of the contracting parties. Project-sensitive technical details, drawings, and contractual information remain confidential.